Gym Timeline - Estimates are Subject to Change

Item         Estimate Status Revised Estimate   Final
                   
DCPD Plan Approval         2/21/08 Mtg. occurred      
Mechanical and Electrical Plans         2/28/08 In process      
Tree Removal             4/12/08    
Earth Disturbance Permit         3/5/08   4/21/08    
Root/Grub Removal             4/26/08    
Ground Lease Signed         3/15/08 Draft sent to Township 4/8/08    
Land Development Plan Approval             4/21/08    
Developers Agreement             5/1/5/2008    
Subcontractor Bids Due         3/25/08        
Finalization of Plans including façade         3/30/08 In process      
Order metal building                  
                   
Rezoning Hearing             5/6/08    
Conditional Use Hearing             5/6/08    
Township Preliminary Final Plan Approval         4/1/08   5/6/08    
Township Final Plan Approval         5/1/08   6/6/08    
Building Permit         5/2/08   6/6/08    
Break Ground         5/3/08   6/ /2008    
Foundation Completed                  
Building Frame Completed                  
Building Facade Completed                  
HVAC Installed                  
Plumbing Completed                  
Interior Walls Completed                  
Bathroom Fixtures Installed                  
Floor Installed                  
Baskets Installed                  
Bleacher Installed                  
Snack Bar Equipment Installed                  
Exterior Walkways Etc. Completed                  
CO Issued         11/25/08        

Last Updated on 4/13/08